November 25, 2025
NEXASIA Data Center — Gijang, Busan
A summary business plan for NEXASIA, a shovel-ready 200MW hyperscale data center site in Gijang, Busan. It walks through the site, a phased development approach, and the market backdrop driving data center demand in Korea.
- Shovel-ready 200MW site with a secured power supply agreement — the first single-lot 200MW in Korea
- Data center zoning and industrial-complex occupancy completed, with data center use codes included
- Phased development across three buildings of 60, 60 and 80 MW
- About 21,000-pyeong site in Gijang, Busan, with strong highway and rail access and low complaint risk
- Busan as a gateway to Korea, where more than 95% of the nation's submarine cables land nearby
- Upgraded Seoul–Busan backbone network (800Gbps / 1.2Tbps) improving latency for the region